Project Workplan

     

2006

     

Milestone I

Analysis and systematization of data
20-Dec-2006

Activities

I.1. Analysis and systematization of existing data

I.2. Design of the website of the project
 

Deliverables

Research report
Project website

 

Status

completed
 

2007

     

Milestone II

Mathematical models and analytical algorithms. Implementation of platform modules (1)
02-Jul-2007

 

Activities

II.1. Establishment of the primary structure of GIS relational databases

II.2. Development of the primary structure of the application
II.3.
Development of the data collection and management module. Design of the structure of the relational databases
II.4.
Development of the generic GIS module
II.5.
Mathematical models and analytical algorithms for the seismic risk analysis modules
II.6.
Update and development of project website

 

Deliverables
Research report
Software modules
Databases (structure)
Updated website
 

 

 

Status

completed
 

Milestone III

Implementation of software modules (2). Assembling of modules
20-Dec-2007

 

 

Activities

III.1. Adaptation of the generic GIS module to the particular steps of the methodology
III.2. Development of risk analysis modules
III.3. Assembling of framework modules
III.4. Update and development of project website

 

Deliverables

Research report
Functional software
Updated website

 

Status

completed

2008

     

Milestone IV

Demonstration of functionality by the testing of the software framework on a pilot zone
30-Apr-2008

 

Activities
IV.1. Testing of the software framework by parametric simulations
IV.2.
Selection and definition of the pilot zone
IV.3.
Database filling for pilot zone
IV.4. Testing of the software framework on pilot zone
IV.5.
Update and development of project website
IV.6.
Improved methodology for the analysis of seismic risk. Part I: Assessment of seismic hazard, data systematization
IV.7.
Writing of papers for the dissemination of project results


 

Deliverables

Research report
Updated website
Papers in conferences

 

 

completed
 

Milestone V

Elaboration of user's manual / presentation of the software framework. Dissemination of results
29-Aug-2008

Activities
V.1. Elaboration of user's manual / presentation of the software framework
V.2. Elaboration of CD-ROM, poster and presentation brochure
V.3. Improved methodology for the analysis of seismic risk. Part II: Seismic vulnerability assessment
V.4. Organization of symposium for the presentation of project results
V.5.
Update and development of project website
V.6. Participation in national and international conferences, publishing of project results in scientific journals in Romania and abroad

 

Deliverables

User's Manual
CD-ROM, poster and brochure
Updated website
Papers in conferences

 

completed